Posted on 31st May, 2019

This is in continuation to the recent notification issued by the Ministry of Finance vide letter no MoF/DNP/GPPMD-08/2018-19/1107 with regard to the revised PRR 2019. Since there have been changes in the evaluation parameters, the online evaluation tool(e-Tool) has to be upgraded to incorporate the changes with effect from 1st July 2019. The development and incorporation of changes will be taking two months time, during which all the procuring agencies following the procurement rules and regulations of the government to abide by the following:

  1. Complete the award of work by 30th June 2019 if you have any open tenders.
  2. All the procuring agencies are reminded  not to carry out any evaluation for procurement of civil works for the period 1st July 2019 to 31st August 2019.
  3. Do not upload any new tenders on e-Tool till 31st of August 2019.
  4. Procuring agencies are advised to make necessary changes in their Annual Procurement Plan in e-Tool and e-GP  accordingly.

The Secretariat will not be liable for any discrepancies that would arise due to non compliance to the above.

This is issued for strict compliance with effect from 1st June 2019 and any inconveniences caused is highly regretted.